Fleet Operator Equipment Enhancement: Replacement of Radio System and Operator Seats
Federal contribution
$1.2M
$1,152,328
Federal share33%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedNov 8, 2017
2018201920202021
Built
Approved 7 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start10 months lateforecast Jan 1, 2017