Heating, ventilation and air conditioning (HVAC) upgrades at Mountain Transit Centre

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$325,000
Federal share50%

of $650.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedMar 19, 2018
201820192020
Built

Approved 12 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
Jul 17, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end12 months lateforecast Mar 31, 2019