Garage Door replacement (32) at Mountain Transit Centre
Federal contribution
$437,361
Federal share33%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
201820192020
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Jun 20, 2017
- Construction end3 months lateforecast Dec 31, 2019
Also in Hamilton