Garage Door replacement (32) at Mountain Transit Centre

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$437,361
Federal share33%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedJul 10, 2017
201820192020
Built

Approved 3 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
Oct 23, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Jun 20, 2017
  • Construction end3 months lateforecast Dec 31, 2019

Also in Hamilton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48135 in the federal list. How to read these figures.