Structural upgrades to Mountain Transit Centre: New transit vehicle wash racks (2) and a covered bus storage area.
Federal contribution
$1.8M
$1,835,209
Federal share38%
of $4.8M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMar 31, 2017
ApprovedJul 10, 2017
2018201920202021
Built
Approved 3 months after the announcement.
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- City of Hamilton
- Construction start
- Oct 23, 2017(actual)
- Construction end
- Jul 31, 2021(actual)
Against the original forecast
- Construction start4 months lateforecast Jul 4, 2017
Also in Hamilton