Structural upgrades to Mountain Transit Centre: New transit vehicle wash racks (2) and a covered bus storage area.

Hamilton, Ontario

completePublic TransitPTIF
Federal contribution
$1.8M
$1,835,209
Federal share38%

of $4.8M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedJul 10, 2017
2018201920202021
Built

Approved 3 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Hamilton
Construction start
Oct 23, 2017(actual)
Construction end
Jul 31, 2021(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 4, 2017