Install Automated Stop Description Device on Buses
Federal contribution
$4,500
Federal share50%
of $9.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 10, 2017
Built
- Program
- Public Transit Infrastructure Fund
- Ultimate recipient
- Corporation of the Town of Huntsville
- Construction start
- May 1, 2017(actual)
- Construction end
- Oct 1, 2017(actual)