BC Ferries Route 28

Vancouver, British Columbia

completeMarineNRP
Federal contribution
$15.1M
$15,096,323
Federal share33%

of $45.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2017
20182019
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Dec 18, 2017(actual)
Construction end
May 2, 2019(actual)

Against the original forecast

  • Construction start8 months lateforecast May 1, 2017
  • Construction end4 weeks earlyforecast May 31, 2019

Also in Vancouver

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48163 in the federal list. How to read these figures.