Back to projects

Install a New Bus Stop Network

Fort Erie, Ontario

completePublic TransitPTIF
Federal contribution
$129,056
Federal share40%

of $320.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMar 31, 2017
ApprovedJul 10, 2017
20182019
Built

Approved 3 months after the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
Town of Fort Erie
Construction start
Jul 1, 2017(actual)
Construction end
Feb 28, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Mar 1, 2017
  • Construction end4 weeks earlyforecast Mar 31, 2019