Norwich Flooding Remediation

Woodstock, Ontario

completeWastewaterCWWF
Federal contribution
$231,667
Federal share42%

of $550.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 26, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Woodstock
Construction start
Jun 9, 2017(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction start13 months lateforecast May 1, 2016