Back to projects

Interior Lining Replacement at Elevated Tank

Spanish, Ontario

completeDrinking WaterCWWF
Federal contribution
$81,464
Federal share50%

of $162.9K total eligible cost; the rest comes from other partners.

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Spanish
Construction start
Jun 12, 2017(actual)
Construction end
Jul 19, 2017(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2017
  • Construction end3 months earlyforecast Oct 31, 2017

Also in Spanish

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48352 in the federal list. How to read these figures.