Federal contribution
$81,464
Federal share50%
of $162.9K total eligible cost; the rest comes from other partners.
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Spanish
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Jul 19, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end3 months earlyforecast Oct 31, 2017