Storm Sewer Outfall Replacement at Ferry Dock in the Hamlet of Corunna

St. Clair, Ontario

completeWastewaterCWWF
Federal contribution
$93,738
Federal share37%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of St. Clair
Construction start
Sep 13, 2017(actual)
Construction end
Nov 13, 2017(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 1, 2017
  • Construction end5 months earlyforecast Mar 31, 2018

Also in St. Clair

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48372 in the federal list. How to read these figures.