Upgrade to primary and secondary clarifier tanks and blowers
Federal contribution
$2.7M
$2,678,132
Federal share50%
of $5.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Peterborough
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 1, 2016
- Construction end3 months earlyforecast Mar 31, 2019