Upgrade to primary and secondary clarifier tanks and blowers

Peterborough, Ontario

completeWastewaterCWWF
Federal contribution
$2.7M
$2,678,132
Federal share50%

of $5.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Peterborough
Construction start
Jul 1, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 1, 2016
  • Construction end3 months earlyforecast Mar 31, 2019