Upgrade/Replace the Sewage Treatment Plant Aeration Equipment

Brooke-Alvinston, Ontario

completeWastewaterCWWF
Federal contribution
$15,000
Federal share38%

of $40.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 1, 2017(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2017

Also in Brooke-Alvinston

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48483 in the federal list. How to read these figures.