Upgrade/Replace the Sewage Treatment Plant Aeration Equipment
Federal contribution
$15,000
Federal share38%
of $40.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of Brooke-Alvinston
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2017
Also in Brooke-Alvinston
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48483 in the federal list. How to read these figures.