Back to projects

Stormwater Quality Control Improvement – Installation Oil/Grit Separators – Multiple Locations

Burlington, Ontario

completeWastewaterCWWF
Federal contribution
$113,920
Federal share34%

of $340.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Burlington
Construction start
Sep 17, 2017(actual)
Construction end
Jun 12, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2017
  • Construction end3 months earlyforecast Sep 1, 2019

Also in Burlington