Roseland Creek Stormwater Erosion Protection – Guelph Line to Upper Middle Road

Burlington, Ontario

completeWastewaterCWWF
Federal contribution
$316,596
Federal share24%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Burlington
Construction start
Aug 14, 2017(actual)
Construction end
Nov 30, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Mar 1, 2017
  • Construction end2 months lateforecast Sep 30, 2018