Inspection and Design of Rail Crossing Culverts – Multiple Locations Along CN Halton and CN Oakville Subdivision Lines

Burlington, Ontario

completeWastewaterCWWF
Federal contribution
$47,501
Federal share15%

of $320.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 25, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Burlington
Construction start
Oct 31, 2017(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start11 months lateforecast Dec 1, 2016
  • Construction end4 months lateforecast Oct 30, 2019