Replacement of Woodward Avenue Storm Sewers (Woodward Avenue and Castleguard Crescent)
Federal contribution
$51,682
Federal share49%
of $105.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 25, 2017
ApprovedMar 27, 2018
2018
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Burlington
- Construction start
- May 15, 2017(actual)
- Construction end
- Oct 3, 2017(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 1, 2017
- Construction end6 weeks earlyforecast Nov 15, 2017
Also in Burlington
- Halton Region Wastewater Treatment (Skyway Facility)$51.4M
- Replacement of Access Points; Open Concept Schools; Building Automation Systems & Controls Upgrade; Child Care Retrofits & Outdoor Spaces$6.9M
- Portable Classroom Ventilation Improvements; HVAC Improvements; Window Replacement$5.6M
- Improvements to HVAC, Windows, Bottle Filling Stations, Washrooms, Doors, Child Care Centre, WiFi and Network Infrastructure$5.4M
- Highway 403 - Rehabilitation and Resurfacing$4.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48494 in the federal list. How to read these figures.