Full watermain and sewer replacement on Hugo Crescent and Lorne Avenue
Federal contribution
$1.5M
$1,523,849
Federal share35%
of $4.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 26, 2017
20182019
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Kitchener
- Construction start
- Apr 3, 2017(actual)
- Construction end
- Dec 31, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Dec 1, 2016
- Construction end3 months earlyforecast Mar 31, 2019
Also in Kitchener
- Stormwater Network Adaptation$50.0M
- Aquatic Centre RBJ Schlegel Park$9.8M
- Installing mechanical ventilation in buildings where none currently exist; Window repair or replacement for fresh air intake$7.9M
- HVAC Upgrades; Upgrading wireless access points; Window replacement; Washroom upgrades; Installing cooling / air conditioning units; room partition replacement$7.6M
- Kitchener Public Library Southwest Community Library$6.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48514 in the federal list. How to read these figures.