Replacement of Existing Pumps at Wastewater Collection Pump Station #2 with Chopper Pumps

Meaford, Ontario

completeWastewaterCWWF
Federal contribution
$34,591
Federal share23%

of $149.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
2018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Municipality of Meaford
Construction start
Jun 5, 2017(actual)
Construction end
Jun 30, 2018(actual)

Against the original forecast

  • Construction end9 months lateforecast Sep 25, 2017

Also in Meaford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48520 in the federal list. How to read these figures.