Rehabilitation of the Stormwater Pond at Mayfield Road and Kennedy Road

Peel, Ontario

completeWastewaterCWWF
Federal contribution
$272,819
Federal share45%

of $600.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2017
  • Construction end6 months lateforecast Sep 30, 2019

Also in Peel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48534 in the federal list. How to read these figures.