Back to projects

Studies to Improve Water Quality Control for Small Watercourses Draining Directly to Lake Ontario

Peel, Ontario

completeWastewaterCWWF
Federal contribution
$62,499
Federal share50%

of $125.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 1, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast Jan 1, 2017
  • Construction end10 months lateforecast Mar 31, 2018

Also in Peel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48537 in the federal list. How to read these figures.