Design for a New Sanitary Trunk Sewer on Lakeshore Road West

Peel, Ontario

completeWastewaterCWWF
Federal contribution
$730,845
Federal share49%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
2017201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Sep 8, 2016(actual)
Construction end
Dec 31, 2019(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 30, 2020

Also in Peel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48539 in the federal list. How to read these figures.