Back to projects

Construction of a 300-mm Water Main on Mount Pleasant Road

Peel, Ontario

completeDrinking WaterCWWF
Federal contribution
$747,919
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
May 31, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start5 months lateforecast Jan 1, 2017
  • Construction end2 years earlyforecast Mar 31, 2022

Also in Peel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48547 in the federal list. How to read these figures.