Upgrades to the Generator Programmable Logic Controllers (PLC) at Various Lake-Based Water Transmission Facilities

Peel, Ontario

completeDrinking WaterCWWF
Federal contribution
$2.0M
$2,000,000
Federal share50%

of $4.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201720182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 17, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start6 months earlyforecast Jul 17, 2017
  • Construction end8 weeks earlyforecast Mar 31, 2019