Back to projects

Replacement of the Existing 400-mm Water Main on Hurontario Street with a 750-mm Water Main

Peel, Ontario

completeDrinking WaterCWWF
Federal contribution
$3.5M
$3,499,900
Federal share50%

of $7.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 23, 2017
ApprovedMar 27, 2018
20182019
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Jan 31, 2019(actual)

Against the original forecast

  • Construction start2 months earlyforecast Aug 14, 2017
  • Construction end8 weeks earlyforecast Mar 31, 2019

Also in Peel

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48558 in the federal list. How to read these figures.