Replacement of the Heart Lake Conservation Area Water Supply System

Peel, Ontario

completeDrinking WaterCWWF
Federal contribution
$250,000
Federal share50%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 1, 2017(actual)
Construction end
Jul 31, 2019(actual)

Against the original forecast

  • Construction start3 months lateforecast Jan 1, 2017
  • Construction end3 months earlyforecast Oct 30, 2019