Back to projects

Trenchless Water Rehabilitation at Multiple Locations

St. Thomas, Ontario

completeDrinking WaterCWWF
Federal contribution
$484,666
Federal share45%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of St. Thomas
Construction start
Aug 1, 2017(actual)
Construction end
Sep 18, 2020(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2017
  • Construction end6 months lateforecast Mar 31, 2020

Also in St. Thomas