Trenchless Water Rehabilitation at Multiple Locations
Federal contribution
$484,666
Federal share45%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedMay 24, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 10 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of St. Thomas
- Construction start
- Aug 1, 2017(actual)
- Construction end
- Sep 18, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2017
- Construction end6 months lateforecast Mar 31, 2020
Also in St. Thomas