Churchill Crescent Reconstruction - Sanitary Sewer, Storm Sewer, & Watermain
Federal contribution
$600,000
Federal share43%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of St. Thomas
- Construction start
- Jun 19, 2017(actual)
- Construction end
- Dec 31, 2017(actual)
Against the original forecast
- Construction start3 months lateforecast Apr 1, 2017