Upgrades to Multiple Sanitary Sewer Pumping Stations (e.g. Installation of Standby Generators)

St. Thomas, Ontario

completeWastewaterCWWF
Federal contribution
$433,333
Federal share43%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of St. Thomas
Construction start
Sep 1, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2017
  • Construction end8 months lateforecast Dec 31, 2017

Also in St. Thomas

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48580 in the federal list. How to read these figures.