Port Weller Wastewater Treatment Plant - Grit Upgrade Program (Retrofitting the existing air lift pumping system to grit pump and cyclonic grit concentrator) - located in the City of St. Catharines

Niagara, Ontario

completeWastewaterCWWF
Federal contribution
$476,667
Federal share47%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 15, 2017(actual)
Construction end
May 23, 2020(actual)

Against the original forecast

  • Construction start6 months lateforecast Feb 24, 2017
  • Construction end5 months lateforecast Dec 31, 2019