Oakes Park Trunk Sewer Relining & Maintenance Hole rehabilitiation - Town of Fort Erie

Niagara, Ontario

completeWastewaterCWWF
Federal contribution
$520,000
Federal share45%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 27, 2017
20182019
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 15, 2018(actual)
Construction end
Apr 30, 2019(actual)

Against the original forecast

  • Construction end8 months earlyforecast Dec 31, 2019