Schedule

Announced and approvedMay 24, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Kapuskasing
Construction start
Oct 5, 2017(actual)
Construction end
Jun 22, 2018(actual)

Against the original forecast

  • Construction start5 months lateforecast May 15, 2017
  • Construction end5 months lateforecast Jan 30, 2018