Replacement of the unstable deteriorated Marksbury Road storm sewer outfall in the City of Pickering to reduce sediment loads to Lake Ontario
Federal contribution
$161,126
Federal share36%
of $450.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
201820192020
Built
Approved 2 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Pickering
- Construction start
- Oct 30, 2018(actual)
- Construction end
- May 31, 2020(actual)
Against the original forecast
- Construction start19 months lateforecast Apr 3, 2017
- Construction end16 months earlyforecast Sep 30, 2021
Also in Pickering
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48623 in the federal list. How to read these figures.