Replacement of the unstable deteriorated Marksbury Road storm sewer outfall in the City of Pickering to reduce sediment loads to Lake Ontario

Pickering, Ontario

completeWastewaterCWWF
Federal contribution
$161,126
Federal share36%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
201820192020
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Pickering
Construction start
Oct 30, 2018(actual)
Construction end
May 31, 2020(actual)

Against the original forecast

  • Construction start19 months lateforecast Apr 3, 2017
  • Construction end16 months earlyforecast Sep 30, 2021