Clarksburg Water and Wastewater Concept Design
Federal contribution
$161,410
Federal share50%
of $322.8K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 16, 2017
ApprovedMar 27, 2018
201820192020
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of The Blue Mountains
- Construction start
- Jun 14, 2017(actual)
- Construction end
- May 1, 2020(actual)
Against the original forecast
- Construction start7 months lateforecast Nov 1, 2016
- Construction end4 weeks lateforecast Mar 31, 2020