Moore Crescent Sewage Pumping Station Renovations
Federal contribution
$90,000
Federal share50%
of $180.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
2018
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of The Blue Mountains
- Construction start
- Feb 6, 2017(actual)
- Construction end
- Nov 30, 2018(actual)
Against the original forecast
- Construction start3 months lateforecast Nov 1, 2016
- Construction end6 months lateforecast May 31, 2018