Upgrade of Minnesota Sewage Pump Station

Collingwood, Ontario

completeWastewaterCWWF
Federal contribution
$422,457
Federal share39%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 16, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Collingwood
Construction start
Nov 1, 2016(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Feb 1, 2020

Also in Collingwood