Replacement of Maple Street Storm Sewer - Replacing 110m of storm sewer between Maple St. & McKay Crt.
Federal contribution
$100,000
Federal share50%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Collingwood
- Construction start
- Oct 27, 2017(actual)
- Construction end
- Dec 1, 2017(actual)
Against the original forecast
- Construction start6 months lateforecast May 1, 2017
- Construction end2 months lateforecast Sep 30, 2017
Also in Collingwood
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48656 in the federal list. How to read these figures.