Back to projects

New upgrade to Wastewater Pumping Station #2 on Right -of-Way on Kelly Street/Peter Street, that services the upper portion of the waste water system

Madawaska Valley, Ontario

completeWastewaterCWWF
Federal contribution
$22,500
Federal share50%

of $45.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Apr 1, 2018(actual)
Construction end
Sep 17, 2018(actual)

Against the original forecast

  • Construction start11 months lateforecast Apr 30, 2017
  • Construction end5 months lateforecast Apr 30, 2018

Also in Madawaska Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48709 in the federal list. How to read these figures.