New Upgrade Replacement to Water Treatment Plant Underdrain Filter #2, Located inside the Water Treatment Plant on Trader Lane

Madawaska Valley, Ontario

completeDrinking WaterCWWF
Federal contribution
$22,500
Federal share50%

of $45.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 25, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jan 15, 2018(actual)
Construction end
Jan 26, 2018(actual)

Against the original forecast

  • Construction start7 months lateforecast Jul 1, 2017
  • Construction end5 months lateforecast Aug 31, 2017