Back to projects

Replacement of Wastewater Treatment Plant Bio-solids Pump, located inside the Wastewater Treatment Plant on Lakeshore Drive

Madawaska Valley, Ontario

completeWastewaterCWWF
Federal contribution
$2,298
Federal share5%

of $44.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jun 1, 2017(actual)
Construction end
Jun 10, 2019(actual)

Against the original forecast

  • Construction end11 months lateforecast Jun 30, 2018

Also in Madawaska Valley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48712 in the federal list. How to read these figures.