Pontiac Pumping Station Drainage Assessment
Federal contribution
$125,000
Federal share50%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Mar 28, 2017(actual)
- Construction end
- Sep 30, 2019(actual)
Against the original forecast
- Construction start8 weeks lateforecast Feb 1, 2017
- Construction end15 months lateforecast Jun 30, 2018
Also in Windsor