Back to projects

St Paul Pumping Station Drainage Assessment

Windsor, Ontario

completeWastewaterCWWF
Federal contribution
$125,000
Federal share50%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
20182019
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Windsor
Construction start
Mar 28, 2017(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Feb 1, 2017
  • Construction end15 months lateforecast Jun 30, 2018

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48760 in the federal list. How to read these figures.