Back to projects

Lou Romano Water Reclamation Plant Main Pumphouse Drywell Integrity and Reliability Improvements

Windsor, Ontario

completeWastewaterCWWF
Federal contribution
$175,000
Federal share50%

of $350.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 12, 2017
201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Windsor
Construction start
Oct 1, 2017(actual)
Construction end
Mar 31, 2020(actual)

Against the original forecast

  • Construction start8 months lateforecast Feb 1, 2017
  • Construction end18 months earlyforecast Sep 30, 2021

Also in Windsor

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48762 in the federal list. How to read these figures.