Supply and Installation of Odour Control system at the Maplewood Pumping Station to prevent collection system corrosion
Federal contribution
$275,000
Federal share50%
of $550.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 12, 2017
20182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Windsor
- Construction start
- May 1, 2018(actual)
- Construction end
- Nov 16, 2019(actual)
Against the original forecast
- Construction start15 months lateforecast Feb 1, 2017
- Construction end9 months lateforecast Feb 28, 2019
Also in Windsor