Separation of existing combined sewers as well as water main and road rehabilitation Princess Avenue, Tecumseh Road East to Adstoll Avenue
Federal contribution
$757,818
Federal share41%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 12, 2017
ApprovedFeb 26, 2018
20182019
Built
Approved 9 months after the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Jun 27, 2017(actual)
- Construction end
- May 30, 2019(actual)
Against the original forecast
- Construction end7 months lateforecast Oct 15, 2018
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48766 in the federal list. How to read these figures.