Storm sewer, wastewater, water main and road rehabilitation on Janisse Drive and Ontario Street

Windsor, Ontario

completeWastewaterCWWF
Federal contribution
$979,716
Federal share47%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2017
ApprovedFeb 26, 2018
20182019
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Windsor
Construction start
Aug 24, 2017(actual)
Construction end
Jan 25, 2019(actual)

Against the original forecast

  • Construction end9 months earlyforecast Oct 15, 2019