Back to projects

Storm sewer, wastewater, watermain, culverts and road rehabilitation

Windsor, Ontario

completeWastewaterCWWF
Federal contribution
$1.5M
$1,478,434
Federal share43%

of $3.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 12, 2017
ApprovedFeb 26, 2018
20182019
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Windsor
Construction start
Jul 31, 2017(actual)
Construction end
Mar 22, 2019(actual)

Against the original forecast

  • Construction start4 months lateforecast Apr 10, 2017
  • Construction end3 weeks lateforecast Feb 28, 2019

Also in Windsor