Replacement and Upgrade of Debris Removal System in the Inlet Works at the Water Pollution Control Plant
Federal contribution
$132,500
Federal share50%
of $265.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 16, 2017
2018
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Orangeville
- Construction start
- Jun 1, 2017(actual)
- Construction end
- Aug 1, 2018(actual)
Against the original forecast
- Construction start4 months lateforecast Feb 1, 2017
- Construction end5 weeks lateforecast Jun 30, 2018
Also in Orangeville
- Dufferin County Administration and Provincial Offences Court Addition$2.7M
- Upgrading of the Water Pollution Control Plant$2.4M
- Rehabilitation of the West Sector Reservoir$2.0M
- Reconstruction of Roads and Services in the South Park and Village Green Subdivisions$1.6M
- New Transfer Terminal and Bus Acquisition$1.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48796 in the federal list. How to read these figures.