Renovation of Ste-Foy water treatment plant – Replacement of ozonation system

Québec, Quebec

completeDrinking WaterCWWF
Federal contribution
$1.4M
$1,380,469
Federal share50%

of $2.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Québec
Construction start
Sep 15, 2016(actual)
Construction end
Oct 8, 2018(actual)

Against the original forecast

  • Construction end6 months earlyforecast Mar 31, 2019