Gaudarville pumping station
Federal contribution
$1.2M
$1,199,295
Federal share50%
of $2.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- City of Québec
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Jun 29, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 31, 2017
- Construction end6 months earlyforecast Dec 31, 2018
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48816 in the federal list. How to read these figures.