Back to projects

Renewal of water pipes

Sainte-Agathe-des-Monts, Quebec

completeDrinking WaterCWWF
Federal contribution
$83,590
Federal share50%

of $167.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 3, 2017
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 2, 2017(actual)
Construction end
Nov 21, 2017(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2017
  • Construction end4 months earlyforecast Mar 31, 2018

Also in Sainte-Agathe-des-Monts

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48824 in the federal list. How to read these figures.